Macau University of Science and Technology - The Construction of the Complex Academic Building of Co
- mingshunconstruction
- 2018年10月3日
- 讀畢需時 1 分鐘
The basement excavation and lateral support system works have been completed in late August 2018, the concreting works of the bottom slab on basement floor B2 were completed on 22nd September 2018; Steel composite columns (total 8 nos) were embedded and installed to nearly the level of the first floor before concreting.
Now we have started to carry out the structure works for the basement floor B1, and plan to finish all the RC works and structural steel works around Chinese New Year in 2019 (including 4 main trusses and composite floor slabs on top of the auditorium).