Arrival Points of the Macau-Taipa Fourth Bridge - Avenida Wai Long
- mingshunconstruction
- 2023年5月18日
- 讀畢需時 1 分鐘
Project No. 4/2021
Project Status as of April 2023
Scope of Work:
The Project is located in Zone E of the new urban landfill area, and the work includes the construction of viaducts from Avenida Wai Long and the maritime terminal Pac On to the Macau-Taipa Fourth Bridge, as well as the reorganization of the sewage and road networks on its periphery, with a construction area about 44,500m2. In order to coordinate the relocation of the electricity network in the area, the construction works will be carried out in two phases. The first phase includes the construction of viaducts from Avenida Wai Long and the maritime terminal Pac On to the Macau-Taipa Fourth Bridge, access ramp to the maritime terminal, a part of the airport access ramp, as well as the road reorganization of the Estrada de Pac On and Pac On Roundabout. The second phase will cover the execution of the remaining part of the airport access ramp, as well as the road reorganization of the north line of Av. Wai Long.
Current Progress:
All works on the first phase of Pak On Avenue and Pak On Circular Road to Pak On Port have been completed and the second phase of the project is currently underway.
The foundation construction is 91% complete, and the road rehabilitation work from south to north of Av.Wai Long is underway, including tree relocation, pipeline relocation in cooperation with franchise companies, reconstruction of sewers, re-paving of sidewalks, re-paving of driveways... and so on, while the overall road work on the northbound line is about 20% complete.
Photos of the Project: