Concepção e Construção de Melhoramento de Emissario Residual da zona ZAPE e NAPE -Progress status

  • mingshunconstruction
  • 2021年11月18日
  • 讀畢需時 1 分鐘

已更新:2021年11月19日

The 1st contractual milestone (Design proposal, Specification, structural and fabricating detail drawings of tunnel boring machine, ELS detail design for the launching shaft) have been achieved. Now we are working for the 2nd contractual milestone.


Furthermore, we have completed the soil improvement and mini-pile works of the launching shaft. The temporary transformer room and external QGBT room for the tunnel boring machine are ongoing. After completed the pipe-pile wall, we can start to work for the ELS and excavation of the launching shaft.


ree

ree

ree

 
 
 

留言


RECENT POSTS

ARCHIVE POSTS

MING SHUN CONSTRUCTION AND PROPERTY INVESTMENT LIMITED.

TEL: (853) 28701611

FAX: (853) 28701622

​EMAIL: mingshun@macau.ctm.net

Luís Gonzaga Gomes Nº14

Edificio King Xiu Garden

Level 1, Andar B e C

Contact Us

Success! Message received.

© 2017 Ming Shun Construction and Property Investment Ltd.

bottom of page