“Construction of Public Housing at Avenida de Venceslau de Morais - Superstructure Work”
- mingshunconstruction
- 2022年11月15日
- 讀畢需時 1 分鐘
Project No. 26/2021
Project Status as of October 2022
Scope of Work:
This project is one part of the public housing construction project under the Macao Public Works Bureau, and our Company is the general contractor of the project. After the project is completed, there will be a three-story basement parking lot and three residential towers. Tower I has a two-story podium with floors 3 to 32 as residential floors; Tower II has a three-story podium with floors 4 to 34 as residential floors; Tower III has a three-story podium with floors 4 to 23 as the residential floors. These 3 towers provide a total of 1,590 units, with 885 T1 type apartments and 705 T2 type apartments. T1 type 885, T2 type 705.
Current Progress:
The construction of the project started on December 30, 2021. At present, the structural construction of the podium and transfer floors of each building has been completed. The structure construction of the tower buildings is now in progress. Tower I is divided into two construction areas, and Tower II is divided into three construction areas, and Tower III has one construction area.
The structure construction of towers I and II has reached the eighteenth floor, and that of tower III has reached the nineteenth floor. The overall structure is expected to be completed on July 11, 2023.
At present, the interior decoration work of these three towers is in progress. The plastering work of Tower I has reached the eighth floor, that of Tower II has reached the seventh floor, and that of Tower III has reached the ninth floor.
This project is estimated to be completed on July 11, 2024.