Construction Project of Temporary Housing Units in Lot C (C1) in Areia Preta Lot P

  • mingshunconstruction
  • 2023年5月18日
  • 讀畢需時 2 分鐘

Project No. 667/2022

Project Status as of April 2023


Scope of Work:

This project (Tender C1), one part of the temporary housing project in Areia Preta Lot P owned by Macau Urban Renewal Limited, comprises the construction of two 41-storey-high and two 50-storey-high residential towers of temporary housing units. After the whole Lot P project is completed, there will be a basement parking lot, a four-storey group building and four residential towers. The basement first floor is the parking lot and the equipment rooms; the ground floor is used for the bus terminal, residential lobbies and parking lot entrance, mechanical and electrical rooms and shops; the first to third floors are used for the parking lots and shops; the fourth floor to the top floors of each building are the green platform and residential floors respectively; there will also be two refuge floors. The total construction area of the buildings is about 161,800 square meters.


The current progress of the project:

As of April 2023, the Temporary Housing Units in Lot C (C1) in Areia Preta Lot P has completed the structure construction of the conversion layer of the tower, with the completion of the conversion floor, the project will usher in the peak period of construction, the standard layer circulation flow operation will become the most important task and goal at present, in order to optimize the construction speed and environmental protection elements, the tower structure will be combined with aluminum formwork and prefabricated stairs for construction, it is expected that each tower will enter the 5-day cycle construction after the completion of the 10th floor structure, with every 2 as units, The goal is to complete the structural cap by the end of this year.

On the other hand, the interior and exterior building renovation and mechanical and electrical system works have also been arranged in an orderly manner to start construction in the middle of the year, and the construction of the standard floor residential construction model room has also been completed, which is now subject to the design and final finalization by the owner, aiming to complete the construction of the walls and ceiling moisture by the end of the year, and the dry work part will be planned to be installed in early 2024.


Photos of the Project:


ree

ree

ree

ree

 
 
 

留言


RECENT POSTS

ARCHIVE POSTS

MING SHUN CONSTRUCTION AND PROPERTY INVESTMENT LIMITED.

TEL: (853) 28701611

FAX: (853) 28701622

​EMAIL: mingshun@macau.ctm.net

Luís Gonzaga Gomes Nº14

Edificio King Xiu Garden

Level 1, Andar B e C

Contact Us

Success! Message received.

© 2017 Ming Shun Construction and Property Investment Ltd.

bottom of page