Construction Project of Temporary Housing Units in Lot C (C1) in Areia Preta Lot P
- mingshunconstruction
- 2023年8月9日
- 讀畢需時 2 分鐘
Project No. 667/2022
Project Status as of July 2023
Scope of Work:
This project (Tender C1), one part of the temporary housing project in Areia Preta Lot P owned by Macau Urban Renewal Limited, comprises the construction of two 41-storey-high and two 50-storey-high residential towers of temporary housing units. After the whole Lot P project is completed, there will be a basement parking lot, a four-storey group building and four residential towers. The basement first floor is the parking lot and the equipment rooms; the ground floor is used for the bus terminal, residential lobbies and parking lot entrance, mechanical and electrical rooms and shops; the first to third floors are used for the parking lots and shops; the fourth floor to the top floors of each building are the green platform and residential floors respectively; there will also be two refuge floors. The total construction area of the buildings is about 161,800 square meters.
Current Progress:
As of July 2023, in terms of main structural engineering, the structural construction of the podium part has been basically completed, the structural construction of the tower part has been completed on the 24th floor, and some towers have been constructed to the 28th floor. According to the current construction speed, T1 and T2 towers The structural topping is expected to be completed in November 2023, and the structural topping of T3 and T4 towers is expected to be completed in December 2023.
In terms of building decoration and mechanical and electrical engineering, the installation of mechanical and electrical piping and muddy water works have started in June 2023. According to the project construction plan, by the end of 2023, the goal is to complete all indoor wall masonry construction and complete 50% of the work.
Photos of the Project:


























留言