The site is divided into three zones for construction: Building A, Building B, and Building C.
Building A, except for its late cast area, all R.C. structural work is completed, E&M and plastering works are proceeding in good order.
Building B, the R.C. structural works is completed to 5th floor, and the remaining is still in progress.
Building C, waterproofing and backfilling works are under construction, while parts of concrete structural works are in progress.