Edifício de Especialidade de Saúde Pública – Superstructure Works - Progress status
2021年11月18日
讀畢需時 1 分鐘
已更新:2021年11月19日
The site is divided into three zones for construction: Building A, Building B, and Building C.
Building A, except for its late cast area, all R.C. structural work is completed, E&M and plastering works are proceeding in good order.
Building B, the R.C. structural works is completed to 5th floor, and the remaining is still in progress.
Building C, waterproofing and backfilling works are under construction, while parts of concrete structural works are in progress.














![Official Launch of [MING SHUN CONSTRUCTION AND PROPERTY INVESTMENT LIMITED. Office in Guangdong-Macau In-Depth Cooperation Zone in Hengqin]](https://static.wixstatic.com/media/2b0dab_57cd0e87eb944ac381689016ee2fc976~mv2.jpg/v1/fill/w_188,h_250,fp_0.50_0.50,q_30,blur_30,enc_avif,quality_auto/2b0dab_57cd0e87eb944ac381689016ee2fc976~mv2.webp)
![Official Launch of [MING SHUN CONSTRUCTION AND PROPERTY INVESTMENT LIMITED. Office in Guangdong-Macau In-Depth Cooperation Zone in Hengqin]](https://static.wixstatic.com/media/2b0dab_57cd0e87eb944ac381689016ee2fc976~mv2.jpg/v1/fill/w_66,h_88,fp_0.50_0.50,q_90,enc_avif,quality_auto/2b0dab_57cd0e87eb944ac381689016ee2fc976~mv2.webp)












留言