Expansion Works of Escola Ilha Verde (The Qingzhou Primary School) - Progress Status
- mingshunconstruction
- 2020年12月2日
- 讀畢需時 1 分鐘
The commencement of the project was in March 2020. At present, the work progress is ongoing smoothly as planned, the R.C. superstructure was completed in early August 2020. Progress of the façade works is 52%, interior fit-out works is 64%, while E&M systems is 50% respectively. Connection of E&M utilities are also in progress, we targeted that it will complete in June 2021. Meanwhile, we believed we can handover the whole project to the client within the contract period.