Project Name: Project No. 30/2024 "Construction of the New Macau Central Library – Demolition, Foundation, and Basement Works"

  • mingshunconstruction
  • 5月19日
  • 讀畢需時 2 分鐘

Project Status as of April 2025


Scope of Work:

This project involves the construction of the New Macau Central Library  at the site of the former Hotel Estoril on the Macau Peninsula, located southeast of Tap Seac Square. Our company is the main contractor for this project and is responsible for the first phase of construction works. The key components include demolition of existing structures, waste disposal, foundation piling, and construction of the basement structure.

The existing four-storey building to be demolished is L-shaped, with a total height of approximately 18 meters and a gross floor area of 2,640 square meters. The demolition area covers around 2,250 square meters.

The excavation support system comprises 593 bored mini piles (273mm diameter), which serve both as temporary earth-retaining structures during construction and as part of the permanent foundation. These will integrate with the reinforced concrete basement walls to form a composite retaining wall. For groundwater control, water-stop steel plates welded between piles and grouted columns outside the excavation form the waterproofing system. A multi-level steel strut system is used for internal support of the excavation. The foundation includes 125 bored mini piles (273mm diameter). The basement structure will be built using conventional reinforced concrete.

The new Macau Central Library is planned to have six levels in total: two basement levels (B2 and B1) designated for parking, book storage and technical facilities; a ground floor serving as the main entrance and lobby, also featuring an auditorium and vehicular access; and three upper floors (1/F to 3/F) primarily for library services, including book collections, reading areas, study zones, computer rooms, exhibition halls and meeting rooms.

Upon completion, the building will maintain its L-shaped configuration. The facade along Avenida de Sidónio Pais will measure approximately 97.0 meters in length and 23.5 meters in width, while the facade along Rua Filipe O'Costa, Sé will be about 62.5 meters long and 15.0 meters wide. The total building height will be +32.00 Msl, with ground level at +11.70 Msl, classifying it as a Class M building.


Current Project Progress:

The overall project progress has reached 69.1% as of now. The first milestone—the demolition of the former Hotel Estoril—has been completed on schedule. The project is currently in its second milestone phase. As of mid-April, the following works have been completed: installation of 719 steel mini piles with a diameter of 273mm, construction of 594 Marshall water-stop piles, erection of steel columns and installation of the steel bridge platform. Ongoing works include: basement steel structural supports (90% complete), basement excavation (80% complete), pile cap formwork (50% complete), and waterproof membrane installation for the basement slab (25% complete).The project is scheduled for completion in December 2025.


Recent photos of the construction site:


ree

ree

ree

ree

ree

ree

ree

ree

 
 
 

留言


RECENT POSTS

ARCHIVE POSTS

MING SHUN CONSTRUCTION AND PROPERTY INVESTMENT LIMITED.

TEL: (853) 28701611

FAX: (853) 28701622

​EMAIL: mingshun@macau.ctm.net

Luís Gonzaga Gomes Nº14

Edificio King Xiu Garden

Level 1, Andar B e C

Contact Us

Success! Message received.

© 2017 Ming Shun Construction and Property Investment Ltd.

bottom of page