Public Housing in Lot B4 in Zone A of the New Urban Landfill Area – Superstructure Work
- mingshunconstruction
- 2023年8月9日
- 讀畢需時 2 分鐘
Project No. 39/2021
Project Status as of July 2023
Scope of Work:
This project is located in Lot B4 in Zone A of the new urban landfill area. It is planned to build a public housing building with 29 floors above ground and three underground floors. This project is the Superstructure work of the building. The lot area of this project is about 10,698 square meters, and the height of the building is 86.45 meters, with a total construction area of 153,088 square meters. The basement three floors will be a public parking lot, providing 498 car parking spaces and 532 motorcycle parking spaces. The ground floor to the second floor will be served as residential lobbies/shops/social facilities. And the third floor is a podium garden. From the 4th to 28th floors, it will be the residential floors, which provides 1575 apartments (including 400 T1 apartments, 525 T2 apartments, and 650 T3 apartments).
This project includes the main structure of reinforced concrete, the indoor and outdoor decoration, and various professional electromechanical installations etc.
The contract start date is March 7, 2022, and the completion date is: September 26, 2024. Structural construction was completed in July 2023 and renovation work is currently underway.
Current progress of the project sludge:
Block I: During the interior renovation of the tower building, the working surface has reached 24F;
Block II: During the interior renovation of the tower building, the working surface has reached 28F. Exterior wall mud and water work has been carried out.
Block III:During the interior renovation of the tower building, the working surface has reached 28F. Exterior wall mud and water work has been carried out.
Block IV:During the interior renovation of the tower building, the working surface has reached 28F. Exterior wall mud and water work has been carried out.
Photos of the Project: